|
New Building for art, design and technology teaching, at King's College School, Wimbledon |
|
|
Designed during 1998-99. Project cost £1.42M
Initial site clearance and preparation of what was originally a playground |
|
|
This sequence of photos shows the construction of the structural elements of the building:
the foundations, columns, floors and roof, over a period of 6 months.
Excavation of foundations |
|
|
|
The subsoil was sand and gravel at 1m depth overlain by made ground. The water table was at 1.6m below ground level. Unforeseen ground conditions: an old soakaway at the foundation position |
|
|
|
Construction of reinforced concrete base pads for columns |
|
|
|
Constructing ground-floor columns and stairwells. The stairwells and lift-shaft provide lateral
stability to the building
|
|
|
|
Installing formwork for insitu-concrete first floor |
|
|
|
Installing reinforcement for first floor |
|
|
|
Placing concrete in 1st floor slab. Some 60m3 were delivered from a nearby ready-mix depot to be placed
in a single continuous pour.
|
|
|
|
1st-floor columns completed. Placing formwork for 2nd floor. First steelwork installed as roof supports. |
|
|
|
Preparing for completion of 2nd floor and uppermost part of lift-shaft |
|
|
|
Starting installation of roof steelwork. The second floor is entirely within the roof-space.
|
|
|
|
Roof steelwork nearing completion |
|
|
|
Roof timberwork being installed on steel frame |
|
|
|
Nearing completion |
|
|
|
Successfully completed and opened |
|